• RE: start an unscheduled job on reactive job or at a specific time

    Hello Sam,

    thank you for the reply.

    Considering the case you are talking, supposing that JOB_A,..,JOB_N are prerequisites for JOB_Work, and this one is scheduled at 9.30, JOB_Work doesn't start when all prerequisites are meet, but just at 9.30.

    I would like to start JOB_Work when all prerequisites are meet AND ALSO at 9.30. Something like:

     - WHEN (JOB_A is true AND ... AND JOB_N is true) OR (TIME = 9.30) THEN START JOB_Work.

    So, if all condition JOB_A,..,JOB_N are meet at 4.30, the JOB_Work must start at 4.30. But it has to start also at 9.30.

     

    As i said is possible with the creation of a new "JOB_scheduled" and put this one as a new prerequisiste in OR condition, but i was asking if possibile to do this without create a new "JOB_Scheduled".

     

    Thank you again,

    Stefano

  • start an unscheduled job on reactive job or at a specific time

    Hi all, 

     

    i have some problems on the configuration of next scenario. Suppose i have the following Jobs:

    - JOBA ..... JOBN

    - JOBWork

     

    All JOBx are prerequisites to the JOBWork in "and condition".... Now i want that the JOBWork start not only when all n-prerequisites are meet, but also at, example, 9.30 of all days... Obviously is possible to create a new JOBY that start daily at 9.30, and add this job as prerequistite to JOBWork in or condition, but i need to maintain a clean situation.

     

    I can't put JOBWork as a time scheduled job because, in this case, if all prerequisties are meet previously than 9:30 the JOBWork doesn't start.

    Can you help me to find another solution than add a new job to this scenario?

    Thank you all,

    Stefano